Brighton Marina seen in a new light.

Ergro has recently completed the renewal of the lighting, emergency lighting, sub-mains and small power systems at a busy nine storey car park in Brighton Marina. The works were completed over a 24 week construction period under a Design and Build contract.

On appointment to the contract Ergro completed a survey and produced up to date structural layout drawings which were provided to the client for future use.

During the delivery of the project Ergro ensured that services to the retail outlets were maintained, this included liaising with the Cinema on a regular basis to keep them up to date with any future/planned car park activities.

The existing car park lighting fittings, containment and cabling and the new LED fittings were replaced providing an 60% saving to utility bills. In addition, the metering system will also allow the client to remotely monitor their energy usage.

The project was delivered on time and to budget; the client was extremely satisfied with the close communication and approach that was taken to working in a live environment, occupied by the general public.

Ergro worked closely with the Marina Management Team to pre-plan the traffic flow, segregation of our staff from the general public and the phasing of the project around periods of high traffic volume.